4th January 2014, 12:46 PM
Must go on......yep it's pretty hot up here but need to prep for the renderers to arrive early next week
removed two rows of bricks for each of the new sliding doors and removed 8x3 ceiling....".a quick trip to bunnings for a 16mm masonry drill as I have discovered we have no power to the pool after yesterday work
Lot a couple of kilos in sweat
We started a couple of months ago with the plan to build a fourth bedroom (not legal height) with a two way ensuite.......we currently have a three bedroom two story brick house and the two boys are sharing a room a fourth room is required
Well the scope has blown out a tad, long story........I decided to lower the concrete floor by 150mm to make the room legal, now need two sliding doors as the original doors were no longer suitable an I removed a window and cut a massive opening for the bedroom, walk in robe, air-con, second lounge all new ceilings, office/study area and the list goes on.............oh and lowering the slab has now caused issues with the drain for the new double shower, it's now lower than the ORG (I think that's what they are called) need to find the sewage line in the back yard now
Oh the joys
Anyway it's about to get exciting back wall and opening to be rendered next week, we can than measure up for the doors, carpenters are book for Monday week for the walls, electrician/ air-con dude later that week, than the plasters Monday fortnight than fit off electrically and air-con followed by painting. If we have enough money the walk in robe will be install, the ensuite will have to wait.
removed two rows of bricks for each of the new sliding doors and removed 8x3 ceiling....".a quick trip to bunnings for a 16mm masonry drill as I have discovered we have no power to the pool after yesterday work
Lot a couple of kilos in sweat
We started a couple of months ago with the plan to build a fourth bedroom (not legal height) with a two way ensuite.......we currently have a three bedroom two story brick house and the two boys are sharing a room a fourth room is required
Well the scope has blown out a tad, long story........I decided to lower the concrete floor by 150mm to make the room legal, now need two sliding doors as the original doors were no longer suitable an I removed a window and cut a massive opening for the bedroom, walk in robe, air-con, second lounge all new ceilings, office/study area and the list goes on.............oh and lowering the slab has now caused issues with the drain for the new double shower, it's now lower than the ORG (I think that's what they are called) need to find the sewage line in the back yard now
Oh the joys
Anyway it's about to get exciting back wall and opening to be rendered next week, we can than measure up for the doors, carpenters are book for Monday week for the walls, electrician/ air-con dude later that week, than the plasters Monday fortnight than fit off electrically and air-con followed by painting. If we have enough money the walk in robe will be install, the ensuite will have to wait.