Hi
I live in SA so our building rules may not apply but in general you will have to apply for approval for demo.
Than you go out to tender for a good price for demo, you want the site completely cleared, all foundations dug up. Down to say 6-800mm.
You want the site level and you need to make sure the power and gas have been removed before demo can start.
Leave water there as the demo guys usually need to water down the building to reduce dust.
On average, demo for a average house is around $10k.
They salvage very little these days as the labour cost is too great.
I suggest you ebay most and get them to remove and pay you that.
Say you get $500 for decking, $1000 for roof etc.
Timber doors and so on.
This may take a bit longer but you will be muchbetter of.
Make sure you tell the demo contractor that these items are going to be stripped beforehand.
After demo, you will probably need temporary fencing to stop people entering and hurting themselves on your site.
Good luck and let the fun begin.