You are all missing the point.
Facts stated are: The contractor placed the concrete as per specified plans.
Various ISO's apply to the application of pouring a slab and its finish.
All you experts in contractual law, please show me where it is stated that the contractor is required to perform his task in inclement weather and still provide the same finished surface as detailed in the applicable standard for concrete finishes.
One fellow even assumes that this contractor was unprofessional. Big call coming from within an air con'd office with no rain falling on his desk.
Stop stirring the pot people and answer the question that was asked by the OP.
Don't give your 2 cents worth of opinion when it is not based on fact.
1991 2 door Disco (current)
2012 Puma ute
2007 D3
1976 2 door RR
1977 2 door RR
1972 FORD XY 4X4
+ 70 other vehicles and trucks
Bookmarks